The Tomils small hydropower plant was constructed during the course of the renovation of the drinking water supply of the municipality of Tomils. The reservoir in Tomils is fed by the overrun from the reservoir in Trans via a new pipeline connection. The water drops 530 metres from the Trans reservoir and drives a Pelton turbine in a separate turbine shaft next to the reservoir in Tomils. The additional costs for the construction of the power station were borne by Entegra Wasserkraft AG, which in return was granted the rights of use to operate the plant.
Facts & figures
Plant Type:
Drinking water power plant
Location:
Tomils, Switzerland
Number of turbines:
1 Pelton, horizontal axis, Zobo Hydropower GmbH
Capacity:
38 kW (0.038 MW)
Shareholding via Entegra:
100 %
Commissioning:
2010
Average annual production:
0.129 GWh
Guided tours:
No
Status:
In service